Cavi Property
Projects
Cambewarra Park
Gantt Timeline
Schedule visualization
SVG
PNG
Phase
Status
Priority
day
week
month
quarter
JUNE 26
JULY 26
AUG 26
SEPT 26
8
15
22
29
6
13
20
27
3
10
17
24
31
7
14
Engage town plan…
Prepare Planning Proposal / LEP amendment (if required)
Submit Development Application (DA)
Council assessment period
Respond to RFI (if issued)
DA approv…
Section 7.12 contri…
Review and discharge DA conditions
Engage civil engine…
Survey — feature and level…
Geotechnical investigation
Civil design — roads, drainage, services
Engineering approval from council / authority
Obtain Construction Certificate (CC)
Prepare civil works contract documents
Tender and appoint civil contractor
Site establishment …
Bulk earthworks and cut/fill
Stormwater drainage installation
Road base and kerb & gutter
Services trenching and conduit installation
Water and sewer connection works
Asphalt and line marking
Landscaping and revegetati…
Final inspection and defects rectification
Occupation Certificate (OC)
Engage su…
Prepare subdivision plan
Section 88B instrument pre…
Council subdivision certificate
NSW Land Registry Services — DP registration
Issue individual ti…
Engage sales agent
Prepare marketing materials
List lots…
Sales campaign — exchange contracts
Settlements
Project c…
Pay devel…
Construction progre…
GST / margin scheme advice
Final project reconciliati…
Today
TASKS
START
DUE
PLANNING & APPROVALS
Engage town planner
10 June
14 June
Prepare Planning Propo…
10 June
3 Sept
Submit Development App…
10 June
24 June
Council assessment per…
10 June
6 Aug
Respond to RFI (if iss…
10 June
24 June
DA approval / consent …
10 June
12 June
Section 7.12 contribut…
10 June
15 June
Review and discharge D…
10 June
1 July
CIVIL ENGINEERING
Engage civil engineer
10 June
15 June
Survey — feature and l…
10 June
17 June
Geotechnical investiga…
10 June
24 June
Civil design — roads, …
10 June
8 July
Engineering approval f…
10 June
8 July
Obtain Construction Ce…
10 June
24 June
Prepare civil works co…
10 June
24 June
Tender and appoint civ…
10 June
1 July
CONSTRUCTION
Site establishment and…
10 June
15 June
Bulk earthworks and cu…
10 June
1 July
Stormwater drainage in…
10 June
24 June
Road base and kerb & g…
10 June
24 June
Services trenching and…
10 June
24 June
Water and sewer connec…
10 June
22 June
Asphalt and line marking
10 June
17 June
Landscaping and revege…
10 June
17 June
Final inspection and d…
10 June
24 June
Occupation Certificate…
10 June
17 June
SUBDIVISION & TITLES
Engage surveyor — subd…
10 June
12 June
Prepare subdivision plan
10 June
1 July
Section 88B instrument…
10 June
17 June
Council subdivision ce…
10 June
1 July
NSW Land Registry Serv…
10 June
8 July
Issue individual titles
10 June
15 June
SALES & MARKETING
Engage sales agent
10 June
17 June
Prepare marketing mate…
10 June
24 June
List lots for sale
10 June
12 June
Sales campaign — excha…
10 June
22 July
Settlements
10 June
1 July
ACCOUNTS & ADMIN
Project cost tracking …
10 June
12 June
Pay development contri…
10 June
12 June
Construction progress …
10 June
15 June
GST / margin scheme ad…
10 June
17 June
Final project reconcil…
10 June
17 June